Source: Mercer County Park Commission E-mail
WEST WINDSOR— The Mercer County Park Commission will hold a third meeting on the development of Dam Site 21 on Tuesday, Nov. 12, from 6:30 to 8:30 p.m. at the Conference Center at Mercer County Community College, 1200 Old Trenton Road in West Windsor. The Park Commission has solicited input from the public on the improvement process by holding forums, focus group meetings and community advisory committee meetings, and through an online survey.
Park Master Plan consultants Simone Collins Landscape Architecture
and Princeton Hydro presented initial ideas at the May public meeting,
including possible improvements and eliciting a wide range of public opinion.
The conceptual design helped identify ideas that are supported and other
concepts that were less popular.
“Our consultant team and the project’s Steering Committee have
carefully considered the many comments from County residents. The draft plan
reflects many of those comments and suggestions and will create a unique
facility that will greatly enhance the environment, while providing for safe
public access and enjoyment of this great resource,” said Park Commission
Executive Director Aaron T. Watson.
The Draft Master Plan will represent the Park Commission’s vision
for long-term improvements to the site. After the meeting, the plan will be
available on the Park Commission’s website (http://mercercountyparks.org/#!/activities/dam-site-21)
for 60 days for public review and comment. The Master Plan will be presented to
the Park Commission for review and approval in early 2020.
Once adopted, the Master Plan will serve as a long-term vision for
improvements to the property and be implemented over multiple phases depending
on funding availability and other factors. Following adoption of the Master
Plan, it is expected that an additional 18 to 24 months will be required to
complete construction documents and to obtain permits to construct a first
phase of improvements. The earliest date for construction of any major park
improvements is projected to be 2022-2023.
The Master Plan analysis identified the site’s important natural
areas as well as existing conditions that are degraded and negatively affect
the site. The project seeks to highlight and enhance the site’s natural
amenities through the restorations of natural areas. The degraded aspects
include:
- Eutrophic pond water, which contains high levels of
nitrogen and phosphorous and is low in oxygen.
- Storm water run-off from surrounding storm drainage
systems negatively affects water quality.
- Many invasive plant species overcrowding and
outcompeting native plant species.
- Areas of heavy deer browse hurting unique site habitats
and destroying understory bird habitat.
- Agricultural field run-off and crop monocultures
affecting water quality, plant species diversity and animal habitats.
The 279 acres of Dam Site 21 includes 49 acres of ponds. On the
230 acres of land area, proposed improvements include:
- 34 acres of reforestation will include several thousand
new trees and 64 acres of new meadows.
- 19 acres of vernal pools that will be fenced to prevent
human intrusion and deer browse to protect this important habitat.
- Approximately 7.9 miles of various trails, including a
1.9-mile segment of the Capital to Coast Trail.
- Kayak access area with parking and restrooms,
waterfront boardwalks as integral components of the trail system, and a
tree canopy walk that will give birders and nature-enthusiasts a unique
perspective of the vernal pools.
Based on public comments received after presentation of the May concept
plan, Draft Plan revisions include:
- Primary park access will be from Old Trenton Road in
West Windsor, secondary access from Line Road in Robbinsville, and minor
access from Hughes Drive in Hamilton at the existing Mercer Soil
Conservation District office. There is no net increase in parking along
Hughes Drive.
- The park’s Core Activities Area is located as far away
from all existing residences as possible, thereby respecting neighbors’
privacy.
- Combs Road will have no major site improvements,
strictly restoration to meadows and trails.
- Playgrounds will be relocated to the Core Activities
Area.
- No shared parking or public trails through the adjacent
Mercer Technical School.
- Elimination of possible future pedestrian access at
Clarion Court.
Of the Miry Run Ponds’ 230
acres of land area, only 17 acres, or approximately 7.4 percent of the site,
would be disturbed for trails, parking and other park visitor facilities. The
site’s valuable natural features will be augmented through the establishment of
34 acres of new forest and 64 acres of native meadow.
More information on this can be found here: https://www.mercercountyparks.org/#!/about/dam-site-21/
Like this:
Like Loading...
You must be logged in to post a comment.