ROBBINSVILLE, NJ (MECER)–As reports were coming in of gas stations running out of gas in the south east United States from the hoarding of gasoline and other fuel products the Colonial Pipeline announced the restart of of the pipeline after a ransomware cyber attack. The company states that it may take several days for the delivery supply chain to return to normal. See press releases from Colonial Pipeline below for the latest updates.
Wednesday, May 12, 5:10 p.m.
Colonial Pipeline initiated the restart of pipeline operations today at approximately 5 p.m. ET.
Following this restart, it will take several days for the product delivery supply chain to return to normal. Some markets served by Colonial Pipeline may experience, or continue to experience, intermittent service interruptions during the start-up period. Colonial will move as much gasoline, diesel, and jet fuel as is safely possible and will continue to do so until markets return to normal.
As we initiate our return to service, our primary focus remains safety. As part of this startup process, Colonial will conduct a comprehensive series of pipeline safety assessments in compliance with all Federal pipeline safety requirements.
This is the first step in the restart process and would not have been possible without the around-the-clock support of Colonial Pipeline’s dedicated employees who have worked tirelessly to help us achieve this milestone. We would also like to thank the White House for their leadership and collaboration, as well as the Department of Energy, Department of Transportation, FBI, PHMSA, FERC and other federal, state and local agencies for their ongoing support.
We will continue to provide updates as restart efforts progress.
###
Tuesday, May 11, 5:15 p.m.
Colonial Pipeline continues to make forward progress in our around-the-clock efforts to return our system to service, with additional laterals operating manually to deliver existing inventories to markets along the pipeline. Markets experiencing supply constraints and/or not serviced by other fuel delivery systems are being prioritized. We are collaborating with the Department of Energy (DOE) to evaluate market conditions to support this prioritization.
Since our pipeline system was taken offline, working with our shippers, Colonial has delivered approximately 967,000 barrels (~41 million gallons) to various delivery points along our system. This includes delivery into the following markets: Atlanta, Ga., Belton and Spartanburg, S.C., Charlotte and Greensboro, N.C., Baltimore, Md., and Woodbury and Linden N.J.
Additionally, in preparation for our system restart, we have taken delivery of an additional 2 million barrels (~84 million gallons) from refineries for deployment upon restart.
Consistent with our safety policies and regulatory requirements, Colonial has increased aerial patrols of our pipeline right of way and deployed more than 50 personnel to walk and drive ~ 5,000 miles of pipeline each day.
Actions taken by the Federal Government to issue a temporary hours of service exemption for motor carriers and drivers transporting refined products across Colonial’s footprint and actions taken by several Governors to lift weight restrictions on tanker trucks should help alleviate local supply disruptions. This is in addition to the Reid Vapor Pressure wavier issued today by the U.S. EPA that will also help alleviate supply constraints in several states serviced by our system. We would like to thank the White House for their leadership and collaboration in resolving this matter as well as the DOE, PHMSA, FERC and other federal agencies for their ongoing support.
Our primary focus remains the safe and efficient restoration of service to our pipeline system, while minimizing disruption to our customers and all those who rely on Colonial Pipeline. We will continue to provide updates as restoration efforts progress.
Related MidJersey.news coverage on Colonial Pipeline incident here:
Update: Colonial Pipeline System Disruption
Cyber Attack Shuts Down Colonial Pipeline
One thought on “Colonial Pipeline initiated the restart of pipeline operations today; Several days to return to normal”
Comments are closed.